The Natural Refurbishment of 1960 Laing Easiform System; Housing Study of the application of natural Hemp Insulation and Fuel Cell Technolgy

download as PDF
Download
as PDF
The Easiform system was in production until early 1970's providing 90 000 units. Proposals are the for natural refurbishment of the Easiform house type. It proposes a combination of natural Hemp insulation, a Fuel Cell CHP boiler and Stainless Steel Vacum Insulated Panels (VIPs) applied to a semi. Hemp Fibre is used as an external render system (u-value 0.16W/m2K) on walls together with low u-value doors and windows achieving an airtightness of 1m3/h.mm2, while maintaining the breathability of the wall. Feasiblity and SAP confirm an annual CO2 emissions total of 17kg/m2. A CHP gas boiler incorporating 1kW fuel cell will generate electricity. The SS VIPs panels provide gnd flr insulation using a thin panel.

Retrofit for the future ZA451G
Images Graphs Figures Description Strategies Building

The Natural Refurbishment of 1960 Laing Easiform System; Housing Study of the application of natural Hemp Insulation and Fuel Cell Technolgy : Project images

Click on image to preview full size

Cost_Benefit_Image-_1.jpg
Cost_Benefit_Image.jpg
DSC00328.jpg
DSC00332.jpg
DSC00334.jpg
DSC00344.jpg
DSC00349.jpg
DSC00351.jpg
DSC00358.jpg
DSC00361.jpg
DSC00368.jpg
Exist_plans_and_elevs.jpg
Prop_Alt_Corner.jpg
Prop_Cill.jpg
Prop_Eaves.jpg
Prop_Edge.jpg
Prop_Head.jpg
Prop_Jamp.jpg
Prop_Typ_Corner.jpg
Prop_plans_and_elevs.jpg
after_prop.jpg
CO2 emissionsPrimary energy requirement
Energy target
Retrofit for the Future

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 4000 kWh/yr 1500 kWh/yr -
Natural gas use17711 kWh/yr 3765 kWh/yr -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement 356 kWh/m².yr 95 kWh/m².yr -
Annual CO₂ emissions 71 kg CO₂/m².yr 20 kg CO₂/m².yr -
Annual space heat demand - 42 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
CHP Fuel Cell Boiler423 kWh/yr -
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
83 kWh/m².yr -
Annual CO₂ emissions
offset by renewable generation
17 kg CO₂/m².yr -

Calculation and targets

Whole house energy calculation method SAP
Other whole house calculation method-
Energy target Retrofit for the Future
Other energy targets1KW electricity will be generated by the CHP boiler used by the household.
Forecast heating load 2.75 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test--

Project description

StageUnder construction
Start date01 April 2010
Occupation date31 January 2011
Location Cymbran Torfaen  Wales
Build typeRefurbishment
Building sectorPublic Residential
Property typeSemi-Detached
Construction typeOther
Other construction type75mm clinker conc-50mm cavity-75mm clinker concrete
Party wall construction200mm clinker concrete
Floor area 85.2
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationMelin Homes
Project lead personWael Nabih, Willdig Lammie Partnership Ltd.
Landlord or ClientMelin Homes Housing Association
ArchitectWael Nabih, Willdig Lammie Partnership Ltd.
Mechanical & electrical consultant Andrew Geens, CEREA University of Glamorgan
Energy consultantMartin Brocklesby, BRE Wales
Structural engineerN/A
Quantity surveyorAndrew Cowling, Property Design and Maintenance, Peterborough
ConsultantSue Duehurst Hemcrete
ContractorProj. Management Contracting; Hemcrete, CERES, Superline Ltd, Melin Homes supply chain

Design strategies

Planned occupancyFamily of three. Two adults and one teenager. Adults alternate working at night.
Space heating strategyThe Micro CHP plant is a totally new design by Ceres Power. The boiler used refluxed gas to power a hydrogen fuel cell and produced both heat and electricity in a 50/50 proportion and with a total output of 1KW. This is supplemented within the same unit by a standard boiler for when the fuel cell output is not high enough. The boiler is designed to be a drop in replacement for an existing condensing boiler unit. All excess electricity produced by the unit is exported to the grid. All excess heat will be stored in the hot water tank. The fuel cell part of the unit has an efficiency of 85% (heat and power) and the standard boiler has an efficiency of 90%. It has been slightly problematical to model this unit in SAP.
Water heating strategySolar Hot Water To minimise the demand for hot water 4.5m2 evacuated tube solar panels have been used. The unit used for SAP modelling is the Thermomax HP100 although other similarly performing units would be acceptable so long as the heat loss coefficient (a1) was less than 1 W/m2K and the zero loss collector efficiency (no) was 0.74 or better.
Fuel strategyMains Gas, Mains electricity with supplementary electricity from the Fuel Cell CHP boiler.
Renewable energy strategyN/A
Passive Solar strategyFront elevation is within 30 degrees of south.
Space cooling strategyNatural Ventilation via windows. Cross ventilation can be achieved using through ventilation between the ground floor living and dining areas.
Daylighting strategyThere are no changes being made to the areas or location of glazing units. All windows will be replaced with same size units but with better U-Values.
Ventilation strategyThis bid does not propose the introduction of new forms of ventilation. Windows are to be used for ventilation.
Airtightness strategy Sap proposes an airtightness of 1m2/h.m2. This is to be ahieved via via parging where appropriate, and providing a rebating doors and windows. We consider that the external render system and the new windows and doors will greatly enhance the air-tightness inside the house.
Strategy for minimising thermal bridges Thermally broken doors and windows incorporated. Door and windows will be located half on the external wall and half of the frame in within the thickness of the external render system. Continuous insulation will be maintained. In addition the cavity will be filled with blown insulation. All jambs will inlcude insulation boards on all sides of the reveal. The roof insulation will be continued to connect with the external render insulation. VIPs are are used for ground floor insulation. In order to avoid bridging, we will make sure that insulation is placed in the cavity below floor level. Full details of the proposals are provided our submission.
Modelling strategyModelling was undertaken only using SAP. Although PHPP was planned, because of time limitations and changes to house type, PHPP was not undertaken.
Insulation strategyWall: Application of external insulation to solid brick walls to achieve a U-value of 0.16W/m2k. Floor: Application of VIPs panel to give 0.23 w/m2K. Roof: Addition of 280mm mineral wool to give 0.12w/m2k. Windows: Nordan thermally broken tripple glazing to give 0.8w/m2k Door: Nordan thermally broken frame to give 1.2w/m2k All window and doors reveals are to have insulation slabs applied to them.
Other relevant retrofit strategiesWe are planning to carry out retrofit works, minimising disruption to tenants who will continue to occupy the proporty. We consider that all our proposals can be delivered with minimal disruption to tenants. In demonstrating this, we consider that there would be little tenant resistance in a roll out programme.
Contextual informationInitial planning consultation has been undertaken. An artist image of post retrofit proposals has been produced and attached to this submission. We note that there has been some concern made by neighbours prior to seeing our proposals. However, we are confident that the proposals will be accepted as there is minimal change in form. Planners have accepted our proposals. Some of the technologies proposed are not available as a market product. These are namely the SS VIPs panels proposed as gnd. fl. insul. and the CHP Fuel Cell boiler. Proto-types are being provided specifically for this bid. Currently their cost is high, but we have provided the cost at which they will be supplied to the market in about a year from now.

Building services

OccupancyNULL
Space heatingNULL
Hot waterNULL
VentilationNULL
ControlsNULL
CookingNULL
LightingNULL
AppliancesNULL
Renewable energy generation systemNULL
Strategy for minimising thermal bridgesNULL

Building construction

Storeys 0
Volume -
Thermal fabric area -
Roof description NULL
Roof U-value 0.00 W/m² K
Walls description NULL
Walls U-value 0.00 W/m² K
Party walls description NULL
Party walls U-value 0.00 W/m² K
Floor description NULL
Floor U-value 0.00 W/m² K
Glazed doors description NULL
Glazed doors U-value 0.00 W/m² K -
Opaque doors description NULL
Opaque doors U-value 0.00 W/m² K -
Windows description NULL
Windows U-value 0.00 W/m² K -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description NULL
Rooflights light transmittance -
Rooflights U-value 0.00 W/m² K