Retrofitting a post Decent Home/Scottish Housing Quality Standard, concrete no-fines property to reach one-eighth of the existing energy use and carbon emissions.

download as PDF
Download
as PDF
Low energy and low carbon retrofitting of a two- bed end-terraced house in Rosyth, Scotland originally built in 1970 s to achieve 85% reductions in carbon emissions. The project s objective is to firstly halve the demand of energy use using passive design and fabric-related energy efficiency measures, then double the efficiency by installing efficient equipment and controls, and finally halve the carbon content of supplies using nominal level of well proven zero carbon technologies, to reach 1/8th of the existing emissions.

Retrofit for the future ZA303S
Images Graphs Figures Description Strategies Building

Retrofitting a post Decent Home/Scottish Housing Quality Standard, concrete no-fines property to reach one-eighth of the existing energy use and carbon emissions. : Project images

Click on image to preview full size

Rosyth-1.jpg
Rosyth-2.jpg
Rosyth_3.jpg
CO2 emissionsPrimary energy requirement
Energy target
Retrofit for the Future

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 904.8 kWh/yr 904.85 kWh/yr -
Natural gas use22834.5 kWh/yr 3566.63 kWh/yr -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement 368 kWh/m².yr 82 kWh/m².yr -
Annual CO₂ emissions 68 kg CO₂/m².yr 16 kg CO₂/m².yr -
Annual space heat demand - 21.49 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
1 kWp photovoltaic panel array833.5999756 kWh/yr -
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
55 kWh/m².yr -
Annual CO₂ emissions
offset by renewable generation
10 kg CO₂/m².yr -

Calculation and targets

Whole house energy calculation method SAP
Other whole house calculation method-
Energy target Retrofit for the Future
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test-13.36m³/m².hr @ 50 Pascals
Final air permeability test--

Project description

StageUnder construction
Start date
Occupation date
Location Rosyth   Scotland
Build typeRefurbishment
Building sectorPublic Residential
Property typeEnd Terrace
Construction typeOther
Other construction type210mm Cast in Situ concrete no fines wall , no insulation
Party wall construction210mm Cast in Situ concrete no fines wall construction
Floor area 77.4
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationHome in Scotland
Project lead person
Landlord or Client
Architect
Mechanical & electrical consultant
Energy consultant
Structural engineer
Quantity surveyor
Consultant
Contractor

Design strategies

Planned occupancy2 occupants, one of them spends most of the weekdays and weekend days in the house.
Space heating strategyHeating from mains gas. High efficiency condensing boiler feeding radiators
Water heating strategySolar hot water, with high efficiency gas condensing boiler back up.
Fuel strategyMains gas and mains electricity
Renewable energy strategySouth-oriented 1 kWp photovoltaic panel array to be installed
Passive Solar strategySolar gains from south facing windows. Efficient building fabric to minimise heat loss.
Space cooling strategyNaturally ventilated house, SAP assessment shows overheating risk 'not significant'.
Daylighting strategyWindow sizes and positioning provide good levels of daylighting throughout the house. Kitchen, living room and dining room achieve a minimum average daylight factor of at least 2%.
Ventilation strategyNatural ventilation through manually openable windows , passive stack ventilation for wet areas.
Airtightness strategy Air - permeability of 3m3/hm2 @ 50 Pa is targeted, highest recommended level for naturally ventilated buildings. Upgradation of windows and doors, minimising thermal bridges and insulating and sealing all air leakage pathways identified in the air pressure test will ensure an airtight fabric is achieved.
Strategy for minimising thermal bridges Using accredited construction details, by detailing for continuous insulation and air barrier on external walls to prevent condensation. Party wall insulation to minimise the thermal bridge between the party wall (back and front) and external wall, and to reduce heat losses to the neighbouring property.
Modelling strategySAP 2005 was used as the primary modelling tool. All SAP calculations were carried out in the approved SAP 2005 software SAPCalc. A PHPP analysis was also carried out for verifying the final package of measures.
Insulation strategyThe concrete no-fines wall will be insulated externally with vacuum insulation panels (VIP) to provide a U-value of 0.17W/m2K. The party wall will be thermally and acoustically insulated to avoid heat loss to the neighbouring property and to reduce noise related issues identified in the occupant survey. The existing pitched roof will be insulated with 250mm of polyurethane to achieve a U-value of 0.1W/m2K. The concrete ground floor slab will be insulated with vacuum insulation panels to minimise increasing the overall thickness of the floor, while still achieving a U-value of 0.2W/m2K.
Other relevant retrofit strategies
Contextual informationA pre-retrofit occupant feedback survey was carried out during Phase 1, to understand the impact of occupant behaviour on energy use. The tenants co-operated enthusiastically and completed a questionnaire survey (both residents) and open-ended interview, which helped us in understanding their satisfaction levels, perception of comfort and control, and their aspirations in the retrofitting project. The tenants also completed logging sheets for thermal comfort and related activities. This survey underpinned the proposed strategies for the retrofit.

Building services

OccupancyNULL
Space heatingNULL
Hot waterNULL
VentilationNULL
ControlsNULL
CookingNULL
LightingNULL
AppliancesNULL
Renewable energy generation systemNULL
Strategy for minimising thermal bridgesNULL

Building construction

Storeys
Volume -
Thermal fabric area -
Roof description NULL
Roof U-value 0.00 W/m² K
Walls description NULL
Walls U-value 0.00 W/m² K
Party walls description NULL
Party walls U-value 0.00 W/m² K
Floor description NULL
Floor U-value 0.00 W/m² K
Glazed doors description NULL
Glazed doors U-value 0.00 W/m² K -
Opaque doors description NULL
Opaque doors U-value 0.00 W/m² K -
Windows description NULL
Windows U-value 0.00 W/m² K -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description NULL
Rooflights light transmittance -
Rooflights U-value 0.00 W/m² K