WARM officeEntered as test to understand Silver standard requirements

download as PDF
Download
as PDF
Upgrade of a 1960s first floor flat to EnerPHit Passivhaus retrofit standard
Images Graphs Figures Description Strategies Building

WARM officeEntered as test to understand Silver standard requirements : Project images

Click on image to preview full size

PHT_awards_2_imagery_Page_001.jpg
PHT_awards_2_imagery_Page_003.jpg
PHT_awards_2_imagery_Page_004.jpg
PHT_awards_2_imagery_Page_006.jpg
PHT_awards_2_imagery_Page_008.jpg
PHT_awards_imagery_Page_001.jpg
PHT_awards_imagery_Page_003.jpg
PHT_awards_imagery_Page_004.jpg
PHT_awards_imagery_Page_005.jpg
finished.jpg
CO2 emissionsPrimary energy requirement
Energy target
AECB Silver

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - 2290 kWh/yr 1835 kWh/yr
Natural gas use- 3410 kWh/yr 1131 kWh/yr
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - 119 kWh/m².yr 73 kWh/m².yr
Annual CO₂ emissions - 25 kg CO₂/m².yr 16 kg CO₂/m².yr
Annual space heat demand - 16 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
119 kWh/m².yr 73 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
25 kg CO₂/m².yr 16 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target AECB Silver
Other energy targets-
Forecast heating load 20 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test01 July 201315m³/m².hr @ 50 Pascals
Final air permeability test02 June 20140.59m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date01 April 2014
Occupation date01 October 2014
Location Plymouth Devon  England
Build typeRefurbishment
Building sectorCommercial
Property typeEnd Terrace
Construction typeMasonry Cavity
Other construction typePUR foam to cavity and EWI added
Party wall construction
Floor area 81
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationWarmhomes
Project lead personpeter warm
Landlord or ClientWARM: Low Energy Buildings Practice
ArchitectBob Woffenden RIBA
Mechanical & electrical consultant WARM
Energy consultantWARM
Structural engineer
Quantity surveyor
Consultant
Contractorwarmhomes

Design strategies

Planned occupancyOffice space for up to 12 people
Space heating strategyExisting gas condensing boiler but half of radiators removed
Water heating strategyExisting gas condensing boiler
Fuel strategyExisting gas boiler and mains electric
Renewable energy strategyNone. Demand reduction primary aim
Passive Solar strategyPassivhaus
Space cooling strategyNight cooling
Daylighting strategyRemove internal walls to form open plan office with better daylightingSwept reveals to windows
Ventilation strategyMVHRDesign to avoid commisssioning
Airtightness strategy Various - ended up PUR foam to cavity walls
Strategy for minimising thermal bridges Good design!EWI, rafter insulation and good windwo installation details
Modelling strategyPHPP
Insulation strategyEWI and rafter insulation and triple glazing
Other relevant retrofit strategies
Contextual informationWas a flat, occupants complained couldn't afford to heat due to draughts. First air test off the scale, retrotec yellow fan could not meet 50 Pa.Ground floor is shop (Ferry Stores), EWI and triple glazing carried down to shop.

Building services

Occupancy8 at present
Space heatingas existing but with half of rads removed
Hot waterExisting gas condensing combi
VentilationMVHR
Controlsroomstat, no time control
CookingExisting electric oven and hob
Lighting5ft T5 hi frequency fittings, and led conversions to down lighters
AppliancesA rate fridge without freeze compartment
Renewable energy generation system
Strategy for minimising thermal bridgesGood Design!

Building construction

Storeys 1
Volume 372
Thermal fabric area 279
Roof description New roof as Grove cottage: strip roof; OSB layer; Airtightness layer; 300mm I beams and insulation; breather membrane, battens, replace tiles
Roof U-value 0.13 W/m² K
Walls description existing cavity walls filled with PUR foam and 200mm neopor EWI
Walls U-value 0.12 W/m² K
Party walls description 25mm laminated plasterboard (18mm insulation 0.022 W/mK)
Party walls U-value 0.75 W/m² K
Floor description Ground: 100mm PIR and floating OSB T&G on existing concrete floorUpper party to shop: Remove services; warmcell injection, airtightness layer sealed to skirtings; T&G OSB floating floor.
Floor U-value 0.20 W/m² K
Glazed doors description Rational Aura plus with triple glazing
Glazed doors U-value 1.23 W/m² K uninstalled
Opaque doors description
Opaque doors U-value - -
Windows description Rational Aura plus
Windows U-value 1.19 W/m² K -
Windows energy transmittance (G-value) 0.51 %
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -

WARM officeEntered as test to understand Silver standard requirements : Download Files