Retrofit of Victorian mid-terrace in Ladybarn, Manchester

download as PDF
Download
as PDF
This was a renovation project of a solid-walled house built in 1888, located in Ladybarn, Manchester. The work included both energy efficiency retrofit measures (e.g. insulation, MVHR) in tandem with some other work as part of the renovation.The energy efficiency measures revolved largely around insulation, airtightness and ventilation.
Images Graphs Figures Description Strategies Building

Retrofit of Victorian mid-terrace in Ladybarn, Manchester : Project images

Click on image to preview full size

2013-07-19_16.jpg
2013-07-31_06.jpg
House_scaffold.jpg
P6180007.jpg
P7010051.jpg
P7170111.jpg
P7260171.jpg
P8160245.jpg
CO2 emissionsPrimary energy requirement
Energy target

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 752.8 kWh/yr - 789 kWh/yr
Natural gas use6244.5 kWh/yr - 4524 kWh/yr
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement 150 kWh/m².yr - 119 kWh/m².yr
Annual CO₂ emissions 29 kg CO₂/m².yr - 23 kg CO₂/m².yr
Annual space heat demand 258.9 kWh/m².yr 89 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
-119 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
-23 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target
Other energy targets-
Forecast heating load 36.6 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test30 May 201312.725m³/m².hr @ 50 Pascals
Final air permeability test13 October 20131.19m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date20 May 2013
Occupation date12 November 2013
Location Manchester Manchester  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeMid Terrace
Construction typeSolid Brick
Other construction type245mm solid brick with finger cavity
Party wall construction
Floor area 60.54
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationColdProof
Project lead personEric Fewster
Landlord or ClientRuth Shepherd
Architect
Mechanical & electrical consultant
Energy consultantEric Fewster
Structural engineer
Quantity surveyor
Consultant
ContractorExpert Home Extensions

Design strategies

Planned occupancyOne person living in the house.
Space heating strategyHeating to be from mains gas-fired boiler feeding radiators; heat recovered from whole house ventilation exhaust.
Water heating strategyWater heated using mains gas-fired boiler only.
Fuel strategyMains gas, mains electricity (but since 2015 from 100% renewable supplier).
Renewable energy strategy
Passive Solar strategy
Space cooling strategy
Daylighting strategy
Ventilation strategyMVHR unit to be installed, openable windows for summer.
Airtightness strategy Airtightness to be achieved using attention to detail at all parts of renovation process. 3 fan tests planned, breathable membrane to be used in front of internal insulation and across first floor ceilings (including passing across top of stud wall), areas of walls within floor voids to be exposed and plastered (for both external and party walls).
Strategy for minimising thermal bridges Thermal bridge modelling to be done on all junctions to reduce heat loss as much as practically possible.
Modelling strategyWhole house modelling was undertaken in PHPP for both pre- and post-retrofit scenarios.
Insulation strategyWood fibre boards to be fixed internally direct onto external-facing walls (no timber studwork needed). Extruded polystyrene laid over existing solid floor - thickness to be determined by existing door thresholds. Mineral wool insulation for the loft space.
Other relevant retrofit strategiesMoisture management was important to get right for both the external solid walls and chimney breasts. For the walls, a combination of wood fibre and external coat of Keim Lotexan mineral paint to repel driven rain was planned. For chimney breasts, we planned to seal off the air vents, yet reduce moisture risk by filling the void with Leca beads, adding a chimney cap to the cowl, painting chimney stack with Keim Lotexan, and removing a brick in the chimney within the loft space to allow air to circulate.
Contextual informationThis project was carried out by myself as energy consultant and project manager. All of the work was done by builders and myself as part of that team (rather than the client). The predicted budget was almost half what was actually spent, but this was a learning project and valuable data on hours spent on each individual improvement was gained as a result. Some compromises were made due to budget available, as well as existing structure (e.g. double glazed windows had recently been put in, and although not high-performing in terms of energy, it did not make sense to take them out). The pre-retrofit gas readings were low since the client had a low average house temperature (only heated 2 rooms).

Building services

OccupancyOne person living in the house.
Space heatingHeating from mains gas-fired boiler feeding radiators; heat recovered from ventilation exhaust.
Hot waterWater heated using mains gas-fired boiler only.
VentilationBrink Sky 300 MVHR unit with an installed (effective) heat recovery efficiency (according to PHPP) of 73.2%. The unit has self-balancing fans, summer bypass and a pre-heating element for cold weather. Air flow is pre-calculated according to the number of bends and length of duct - actual flow is then restricted accordingly at the manifold prior to distribution to the various terminals. Existing windows openable for summer ventilation if needed.
ControlsDigital controller for MVHR.
CookingGas oven/hob.
Lighting100% compact fluorescents
AppliancesA-rated fridge/freezer unit, microwave and washing machine.
Renewable energy generation system
Strategy for minimising thermal bridgesThermal bridge modelling was done on all junctions in order to reduce psi-value as close to zero as possible. The highest value ended up being certain window frames to walls (0.087 W/mK). All other junctions were negative or just above zero. Some were fine as they were, others required modelling with strips of Spacetherm-P (a product that weds aerogel to plasterboard). Junctions requiring this were: (1) Loft to party wall, (2) Solid floor to party wall, and (3) External wall to party wall (in vertical plane).

Building construction

Storeys 2
Volume 167
Thermal fabric area 270
Roof description Bathroom loft: insulation was done using mineral wool to end up with 320mm thick, giving a finished roof u-value of 0.127 W/m2K. There was some mineral wool there already, but not very much we therefore topped it up a fair amount. Main loft: insulation was done using mineral wool to end up with 300mm thick, giving a finished roof u-value of 0.134 W/m2K. In this case, most of the insulation was already there, we just topped it up.Both ceilings were finished with an airtightness membrane (Intello) that was stapled to batons that had been fixed to loft joists through the existing plastered ceiling, and sealed with Orcon-F to solid plastered walls. This entailed cutting through the top of a stud wall between the stairs and bedroom to allow the membrane to pass, which in turn required that the stud wall was reinforced using a wood frame above the stairs. An airtight loft hatch with ladder was installed in one bedroom.
Roof U-value 0.13 W/m² K
Walls description The external-facing walls of the main house were insulated internally using wood fibre boards 80mm thick. These were fixed directly to the solid wall with concrete screws and plastic washers. Insulation was continuous through floor void, which entailed cutting out floorboards and ceiling plasterboard to accommodate it. We decided not to insulate the bathroom walls internally due to limited space. Insulation could have been done with Spacetherm-P, but since the walls already had cavity wall insulation, the low energy savings vs high cost did not seem to make economic sense. An airtight membrane (Intello) was put in front of the wood fibre boards, followed by batons for the service zone, all fixed in place by concrete screws. Naidec double-sided tape had to be used over the drill hole (just after drilling through but just prior to inserting the screw) to ensure airtightness. Outside, the walls were treated with Keim Lotexan to reduce moisture from driven rain.
Walls U-value 0.36 W/m² K
Party walls description Party walls were not insulated. However, the part of the wall within the floor void was exposed and plastered for airtightness reasons.
Party walls U-value 1.52 W/m² K
Floor description The existing solid floor was insulated using extruded polystyrene (Marmox) 20mm thick, laid with tile grout on solid floor, followed by underlay and 8mm laminate.This was one compromise we made to avoid digging up the existing floor. Insulation thickness was dependent on the existing door thresholds.
Floor U-value 1.06 W/m² K
Glazed doors description
Glazed doors U-value - -
Opaque doors description These were not replaced windows and doors had recently been replaced prior to the refurbishment, so given the other work to do, the client understandably did not feel like spending more money on this element.
Opaque doors U-value 1.70 W/m² K uninstalled
Windows description These were not replaced windows and doors had recently been replaced prior to the refurbishment, so given the other work to do, the client understandably did not feel like spending more money on this element. Window reveals were insulated with 20mm wood fibre board, and the airtight membrane was continued over this up to the frame where it was taped to it using airtightness tapes.
Windows U-value 2.65 W/m² K -
Windows energy transmittance (G-value) 65 %
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -

Retrofit of Victorian mid-terrace in Ladybarn, Manchester : Download Files