Harrow Road Retrofit

download as PDF
Download
as PDF
This 1952 solid wall detached house in Nottingham was extended and refurbished using the EnerPHit standard as a guide. PHPP predicted a space heating demand of 25 kWh/m2.a (assuming 1 ACH at 50Pa). Measured energy demand in the 12 months to May 2014 was 20 kWh/m2.a (although air tightness currently exceeds 1 ACH). Comfort and air quality are vastly better than before the refurbishment, a change which is reflected in before and after datalogger records of temperature and relative humidity.
Images Graphs Figures Description Strategies Building

No images have been supplied for this project

 

CO2 emissionsPrimary energy requirement
Energy target
EnerPHit was used as a guide

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Renewable electricity generation This project has used the contributions from renewable electricity generation equipment to either meet the Retrofit for the Future target or otherwise reduce the Primary energy requirement and CO₂ emissions associated with the project.

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 1560 kWh/yr 1590 kWh/yr 1445 kWh/yr
Natural gas use21800 kWh/yr 5345 kWh/yr 4509 kWh/yr
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement 232 kWh/m².yr 81 kWh/m².yr 70 kWh/m².yr
Annual CO₂ emissions 43 kg CO₂/m².yr 16 kg CO₂/m².yr 14 kg CO₂/m².yr
Annual space heat demand 202 kWh/m².yr 25 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
PV panels-3108 kWh/yr
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
81 kWh/m².yr 8 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
16 kg CO₂/m².yr -1 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target EnerPHit was used as a guide
Other energy targets-
Forecast heating load 1.3 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test16 August 20121.093m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date21 October 2011
Occupation date21 October 2012
Location Nottingham Nottinghamshire  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeDetached
Construction typeSolid Brick
Other construction type9 inch solid brick wall
Party wall construction
Floor area 125
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

Organisation
Project lead personTina Holt
Landlord or ClientTina Holt and Richard Middup
ArchitectGil Schalom
Mechanical & electrical consultant Andrew Farr - Green Building Store (MVHR)
Energy consultantAlan Budden - Eco Design Consultants (PHPP)
Structural engineerAndy Marlor - Howard Ward Associates
Quantity surveyornone
Consultantnone
ContractorMcCane Construction & Ian Brown Joinery

Design strategies

Planned occupancy2 adults, 2 children (1 adult working from home)
Space heating strategyHeating from gas combi boiler feeding radiators. Whole house MVHR.
Water heating strategyHot water from gas combi boiler.
Fuel strategyMains gas for hot water and heating.Mains electricity for cooking, lighting etc.
Renewable energy strategy3.25 kWp PV panel array
Passive Solar strategyThe street runs N-S so most windows face east and west. To improve passive solar gain, the new extension includes a south facing window and the new loft conversion has a south facing rooflight.
Space cooling strategyThe existing brick walls and new blockwork are externally insulated so provide thermal mass. In very hot weather, windows (and some curtains) are closed, ventilating only with MVHR. Once the outside temperature falls below internal air temperature, windows are opened to allow passive stack cooling.
Daylighting strategyThe existing east and west facing windows were already quite generous. Extensive patio doors on the west side provide light into the extension, aided by a light colour scheme.We replaced the solid panels on the stairs with spindles to allow more light into the hall and landing from the reduced north facing windows.
Ventilation strategyMVHR and opening windows (which allow passive stack ventilation)
Airtightness strategy The air tightness layer is internal: plaster on the existing brick walls and the new block walls, air vapour barriers in the attic and the square bay (timber construction).
Strategy for minimising thermal bridges Thermal bridges minimised by careful detailing at all junctions and closely overseen during the build. Heat loss via walls to ground minimised with insulation downstands below ground floor insulation and EWI continuing to footings of the existing house.
Modelling strategyPHPP
Insulation strategy- Application of external insulation to solid brick walls (to achieve U-value of 0.13 W/m2K)- Removal of existing suspended and solid floors and replacement with solid insulated floor (to achieve U-value of 0.1 W/m2K)- Insulation above and between rafters (to achieve U-value of 0.13 - 0.10 W/m2K).
Other relevant retrofit strategiesFamily moved out and rented a house near by. This was useful to store stripped out items for re-use (e.g. timbers, floorboards) and new items until installation (e.g. windows, MVHR)
Contextual informationThe house was not bought with a Passive House refurbishment in mind at the outset, and the E-W orientation is not ideal. The plot is narrow so there is little gap between this house and the neighbouring houses to north and south. This made scaffolding for EWI difficult on one side, and means that the original house had no south facing windows.Planning permission was sought to insulate and render all elevations (originally all brick) but in the end the compromise was to use brick slips on the bays.The existing brickwork was spalling badly in places so needed protection of some sort.

Building services

OccupancyAs before the refurbishment - 2 adults, 2 children
Space heatingATAG A-rated gas combi boiler (located in an insulated plant room outside the envelope) feeding 5 small radiators
Hot waterATAG gas combi boiler (located in an insulated plant room outside the envelope)
VentilationPaul Focus 200 MVHR unit with Lindab ducting supplied and designed by Green Building Store
ControlsGas boiler thermostat and MVHR controls in main living area, TRVs on 4 radiators
CookingElectric induction hob and oven
LightingMainly LEDs. Some CFLs.
AppliancesA+++ rated fridge freezer. dishwasher. washing machine
Renewable energy generation system3.25 kW PV panel array on S facing roof
Strategy for minimising thermal bridgesSome detailed calcs were carried out in the design of the square bay (which was re-built as the original curved bay was weak). Otherwise standard details were used.

Building construction

Storeys 3
Volume -
Thermal fabric area -
Roof description Pitched roof with gable end to rear and smaller gable over front bay. Stick built with 150mm rafters, 100mm foil faced PIR insulation above the rafters and 150mm Rafter Roll 32 between the rafters.
Roof U-value 0.13 W/m² K
Walls description 9 inch brick wall (exisitng) and 140mm block (extension) with 180mm Phenolic foam board external insulation finished with render and brick slips on the bays
Walls U-value 0.13 W/m² K
Party walls description
Party walls U-value -
Floor description 300mm XPS under the whole ground floor, with downstands to the footings around every internal and external wall. 100mm upstands of XPS with 20mm foil faced PIR upstands above (keeping the slab and the screed away from the brick walls)
Floor U-value 0.10 W/m² K
Glazed doors description Green Building Store EcoPassiv front and back door
Glazed doors U-value 0.75 W/m² K -
Opaque doors description
Opaque doors U-value - -
Windows description Green Building Store EcoPassiv windows
Windows U-value 0.75 W/m² K -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description Quad glazed Fakro rooflight with insulated flashing
Rooflights light transmittance -
Rooflights U-value -