Due to tricky site conditions and planning constraints, this 2 bed bungalow had to be built on one level which resulted in a challenging building form with a high ratio of heat loss area to useable floor space. The design team successfully overcame these challenges resulting in the building meeting the strict Passivhaus standards and an average U value for walls, floor and roof of 0.08W/m2K.
Images Graphs Figures Description Strategies Building

Craigrothie : Project images

Click on image to preview full size

Craigrothie.jpg
CO2 emissionsPrimary energy requirement
Energy target
PassivHaus

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - - -
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - - -
Annual CO₂ emissions - - -
Annual space heat demand - - -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
--
Annual CO₂ emissions
offset by renewable generation
--

Calculation and targets

Whole house energy calculation method
Other whole house calculation method-
Energy target PassivHaus
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test--

Project description

StageOccupied
Start date
Occupation date01 October 2011
Location Craigrothie Fife  Scotland
Build typeNew build
Building sectorPrivate Residential
Property typeDetached
Construction typeOther
Other construction type
Party wall construction
Floor area 81
Floor area calculation method Treated Floor Area (PHPP)
Building certification  Passivhaus certified building Passivhaus certified building

Project Team

OrganisationPassivhaus Associates
Project lead person
Landlord or ClientGeum Limited
ArchitectLocate Architects
Mechanical & electrical consultant Morgan Associates
Energy consultant
Structural engineer
Quantity surveyorJohn Duguid Partnership
ConsultantCertifier - Peter Warm
ContractorW H Brown Construction (Dundee) Ltd

Design strategies

Planned occupancy
Space heating strategy
Water heating strategy
Fuel strategy
Renewable energy strategy
Passive Solar strategy
Space cooling strategy
Daylighting strategy
Ventilation strategy
Airtightness strategy
Strategy for minimising thermal bridges
Modelling strategy
Insulation strategy
Other relevant retrofit strategies
Contextual information

Building services

Occupancy
Space heating
Hot water
Ventilation
Controls
Cooking
Lighting
Appliances
Renewable energy generation system
Strategy for minimising thermal bridges

Building construction

Storeys
Volume -
Thermal fabric area -
Roof description
Roof U-value -
Walls description
Walls U-value -
Party walls description
Party walls U-value -
Floor description
Floor U-value -
Glazed doors description
Glazed doors U-value - -
Opaque doors description
Opaque doors U-value - -
Windows description
Windows U-value - -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -