The Curly House

download as PDF
Download
as PDF
Initial project meetings first started in January of 2008, the clients owned a small cottage on the site which had been extended several times during the 80's and had permission to make further adaptations. The mixture of building standards meant that their home was extremely drafty and very energy inefficient. The site itself is particularly exposed.The client knew from an early stage that they would be using there trusted friend Antoine Costantini of Kithurst Builders for the main contractor on the project. Ecotecture ltd were appointed along side Peter Rainier of DMH Stallard as the planning consultants.Planning was achieved on the site despite its being in an AONB and an area of development restriction. The design which achieved planning permission was a crescent form which steps and slides into the slopes on the site. The crescent formation is in direct response to solar orientation.
Images Graphs Figures Description Strategies Building

The Curly House : Project images

Click on image to preview full size

DSC02854.jpg
First_coat_of_render_applied_to_the_exterior.jpg
Front_entrance.jpg
curved_filnt_wall_1.jpg
curved_filnt_wall_2.jpg
internal_shot.jpg
new_screed_in_lounge-dining_room.jpg
CO2 emissionsPrimary energy requirement
Energy target
Passivhaus

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - - -
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - - -
Annual CO₂ emissions - - -
Annual space heat demand - 3 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
--
Annual CO₂ emissions
offset by renewable generation
--

Calculation and targets

Whole house energy calculation method OTHER
Other whole house calculation methodIES thermal model developed by an independent consultant.
Energy target Passivhaus
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test--

Project description

StageUnder construction
Start date31 January 2009
Occupation date31 August 2011
Location Chichester West Sussex  England
Build typeNew build
Building sectorPrivate Residential
Property typeDetached
Construction type
Other construction type
Party wall construction
Floor area 407.8
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationEcotecture Ltd
Project lead personKithurst Builders
Landlord or ClientNot given
ArchitectEcotecture Ltd
Mechanical & electrical consultant Kithurst Builders
Energy consultantJohn Packer Associates
Structural engineerBLB Structural Engineers
Quantity surveyor
ConsultantKithurst Builders - Design proportion allocated in contract documentation
ContractorKithurst Builders

Design strategies

Planned occupancyThe brief was to design a building which would accommodate the family for many years into the future, the planned occupancy would be for 5 adults. Additionally, the home will be used for large family occasions. A requirement was set for a minimum 16 seated spaces to be available for dining during these family occasions.
Space heating strategyThe space heating strategy is that of Passivhaus, the primary energy supply from space heating will be from internal heat gains.Thermal modelling shows the property achieve a lower than Passivhaus demand per m2 of space heating.
Water heating strategyTwo evacuated tube solar thermal panels are backed up by a small LPG boiler.
Fuel strategy
Renewable energy strategy
Passive Solar strategy
Space cooling strategy
Daylighting strategy
Ventilation strategyThe ventilation system is a Paul MVHR system designed and supplied by Green Building Store.
Airtightness strategy Initial tests show the project achieving 0.3m3/m2/hr at 50 pascals. The use of the Nudura ICF in combination with the OpDeck floor system provides excellent base level air tightness, with extremely low movement within the structure itself.The contractor has sourced and installed OptiWin Passivhaus certified windows which are also a key ingredient to the air tightness approach.
Strategy for minimising thermal bridges
Modelling strategy
Insulation strategy
Other relevant retrofit strategies
Contextual information

Building services

Occupancy
Space heating
Hot water
Ventilation
Controls
Cooking
Lighting
Appliances
Renewable energy generation system
Strategy for minimising thermal bridges

Building construction

Storeys
Volume -
Thermal fabric area -
Roof description
Roof U-value -
Walls description
Walls U-value -
Party walls description
Party walls U-value -
Floor description
Floor U-value -
Glazed doors description
Glazed doors U-value - -
Opaque doors description
Opaque doors U-value - -
Windows description
Windows U-value - -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -