Tuxford - A1 Housing Association.

download as PDF
Download
as PDF
The existing pre-cast concrete panel construction and orientation led us to a solar strategy, which utilises the inherent thermal mass of the internal walls. The fabric solution was detailed to ensure there is no de-bonding of the concretes ability to absorb and radiate heat contributing to internal temperature regulation and a comfortable environment for the tenant. Combining an air source heat pump, low temperature distribution system, whole house mechanical ventilation (MVHR) and photovoltaic electricity generation into a coherent renewable strategy complements the solar/ thermal mass approach. Thermaskirt heating distribution was selected due to its innovative delivery of heat low down in the room avoiding inefficient convection.

Retrofit for the future ZA525R
Images Graphs Figures Description Strategies Building

Tuxford - A1 Housing Association. : Project images

Click on image to preview full size

16045_00_01.jpg
16045_00_04.jpg
16045_00_05.jpg
16045_00_06.jpg
16045_00_07.jpg
16045_00_11.jpg
A1_-_3D_model.jpg
A1_-_Heating_Plant_Sensible_Load__Living_room.jpg
A1_-_SAP_DSM_comparison.jpg
A1_colour_section.jpg
CO2 emissionsPrimary energy requirement
Energy target
Retrofit for the Future

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 968.27 kWh/yr 3395.04 kWh/yr 10038 kWh/yr
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
house coal 21283.04 kWh/yr - -
 Pre-developmentForecastMeasured
Primary energy requirement 284 kWh/m².yr 96 kWh/m².yr 283 kWh/m².yr
Annual CO₂ emissions 98 kg CO₂/m².yr 23 kg CO₂/m².yr 67 kg CO₂/m².yr
Annual space heat demand - 38 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
PV panels1667.199951 kWh/yr -
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
49 kWh/m².yr 283 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
12 kg CO₂/m².yr 67 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method SAP
Other whole house calculation method-
Energy target Retrofit for the Future
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test-7.02m³/m².hr @ 50 Pascals
Final air permeability test-3.26m³/m².hr @ 50 Pascals

Project description

StageUnder construction
Start date01 March 2010
Occupation date30 April 2010
Location Tuxford Nottinghamshire  England
Build typeRefurbishment
Building sectorPublic Residential
Property typeMid Terrace
Construction typeOther
Other construction typePrecast concrete panel, render and tile finish. 70mm insulation
Party wall constructionUninsulated precast concrete panel
Floor area 88.64
Floor area calculation method Treated Floor Area (PHPP)
Building certification

Project Team

OrganisationConnaught Partnership Limited
Project lead personConnaught Partnership Limited
Landlord or ClientA1 Housing Association
ArchitectStroma Design
Mechanical & electrical consultant Stroma Design/ Stroma Technology
Energy consultantStroma Design/ Stroma Technology
Structural engineerAdept Civil and Structural Consulting Engineers
Quantity surveyorConnaught Partnership Limited
Consultant
ContractorConnaught Partnership Limited

Design strategies

Planned occupancyThere are currently 4 occupants, 3 Adults and a child. The property is occupied for most of the day and one of the occupants works night shift.
Space heating strategySpace heating from air source heat pump with Thermaskirt heating distribution. Controls from weather compensator and time and temperature zone control.
Water heating strategyWater heating from air source heatpump feeding 210l thermal store with 50mm insulation and electric immersion back up.
Fuel strategyMains electricity and electricity generated from PV.
Renewable energy strategy2 kWp photovoltaic panel array orientated South.
Passive Solar strategyHouse is orientated due South.
Space cooling strategyNatural ventilation for most of the cooling season. MVHR unit has an automatic summer bypass valve to prevent exit air from the dwelling heating fresh incoming air during hot periods. This function is desirable during summer nights when outside air temperature is cooler than inside air temperature, therefore providing a cooling function.
Daylighting strategyExisting kitchen achieves an average daylight factor of at least 2%. The living room, dining room and study achieve average daylight factor of at least 1.5%.
Ventilation strategyMVHR and openable windows for summer ventilation.
Airtightness strategy Through extensive experience in Air testing we initially identified the key areas that contribute to poor air permeability tests results Our approach relies on communicating the details required to those on site who will implement them. The concrete floor is sealed to the wall to the entire perimeter. Plasterboard ceiling taped to wall, all joints in plasterboard taped. Penetrations in plasterboard to be mastic sealed. Plaster finish to walls to cover sealed floor/wall and ceiling wall/junctions. Reveals where thermal laminate board is to be installed to receive continuous strip of sealant, window board fixed on layer of compressible regupol to create air tight seal. Timloc insulated, air sealed loft hatch. External doors to Air Permeability standard in BS 6375: 1-2004 All windows and doors to receive continuous mastic seal to frame. All penetrations in denoted in elements above to be mastic sealed.
Strategy for minimising thermal bridges Careful detailing and consideration in section, plan and 3 dimensions ensures we achieve an excellent Y-value. A continuous thermal envelope is implemented and aided by the use of the external insulation system. External wall insulation extends below ground level to minimise the lateral thermal transmission. At roof level the external wall insulation extends into the eaves and wraps the head of the pre-cast concrete panel to maintain continuity with the roof insulation. Windows and doors are thermally broken and reveals and heads provide a secondary thermal barrier in the form of thermal laminate board. The existing concrete floor insulated with Specetherm is the only separated element in the otherwise continuous thermal envelope.
Modelling strategyThe method of assessment used to develop the performance figures is SAP 2005 and the TSB extension sheet. The design process has used Dynamic Simulation Modelling (DSM), which is a more flexible design tool and allows for on going design improvements and management of building use. The DSM modelling has also allowed a comprehensive comparative analysis, reflecting the profile assigned within SAP and also the actual expected usage profile and temperature set points agreed with the tenant. This analysis should provide a close approximation of the actual energy use monitored by EST following the implementation of the improvements.
Insulation strategyExternal walls to receive NBT Pavatex Diffutherm a 95% recycled product achieving a u-value of 0.18 W/mK Roof to receive 300mm Thermafleece a natural, sustainable product achieving a u-value of 0.13W/mK. Ground floor solid slab topped with 10mm Spacetherm, unrivalled in its thermal conductivity. Its application combined with Fermacell protection board ensures a good thermal resistance with minimal disruption.
Other relevant retrofit strategiesThe design approach has been to benchmark, improve the fabric using appropriate materials and measures, reduce the energy load and provide heat and energy from appropriate technologies. Other considerations have included specific issues with house construction, setting, type, applicability/repeatability, planning & building regulation requirements and aesthetics. Briefing from the tenant and house provider has been integrated in this process.
Contextual informationThe existing pre-cast concrete panel construction and orientation led us to a solar strategy which utilises the inherent thermal mass of the internal walls. The fabric solution was detailed to ensure there is no de-bonding of the concrete's ability to absorb and radiate heat contributing to internal temperature regulation and a comfortable environment for the tenant. Careful consideration was given to summer and winter solar azimuths that helped us determine reveal depths ant the use of external shading devices. The already existing external render allowed us to utilise a higher performing external insulated render system with minimal visual impact. The orientation provided a platform for solar technologies in the form of PV.

Building services

OccupancyNULL
Space heatingNULL
Hot waterNULL
VentilationNULL
ControlsNULL
CookingNULL
LightingNULL
AppliancesNULL
Renewable energy generation systemNULL
Strategy for minimising thermal bridgesNULL

Building construction

Storeys
Volume -
Thermal fabric area -
Roof description NULL
Roof U-value 0.00 W/m² K
Walls description NULL
Walls U-value 0.00 W/m² K
Party walls description NULL
Party walls U-value 0.00 W/m² K
Floor description NULL
Floor U-value 0.00 W/m² K
Glazed doors description NULL
Glazed doors U-value 0.00 W/m² K -
Opaque doors description NULL
Opaque doors U-value 0.00 W/m² K -
Windows description NULL
Windows U-value 0.00 W/m² K -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description NULL
Rooflights light transmittance -
Rooflights U-value 0.00 W/m² K