Harpenden EnerPHit Plus

download as PDF
Download
as PDF
Deep retrofit of a 1960s detached house in Harpenden and the addition of a small rear extension. This project was constructed to meet the EnerPHit Plus criteria as well as going gas free; by using an air source heat pump and harnessing renewable energy with an entire roof pitch dedicated to solar pv. The existing brickwork walls were externally insulated using wood fibreboard and finished with a painted render and the curtain walls were removed and replaced with new highly insulated timber I beam walls with cellulose insulation and clad in western red cedar. The rear single storey extension was also constructed in this way and finished with either render or timber cladding. The existing ground floor was removed and replaced with a new highly insulated slab with underfloor heating.
Images Graphs Figures Description Strategies Building

Harpenden EnerPHit Plus : Project images

Click on image to preview full size

IMG_8584.jpg
34_SD_Rd.jpg
Rear.jpg
CO2 emissionsPrimary energy requirement
Energy target
EnerPHit

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - - -
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - - -
Annual CO₂ emissions - - -
Annual space heat demand - - -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
--
Annual CO₂ emissions
offset by renewable generation
--

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target EnerPHit
Other energy targets-
Forecast heating load -

Airtightness

 DateResult
Pre-development air permeability test10 December 20198.39m³/m².hr @ 50 Pascals
Final air permeability test08 November 20210.59m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date13 January 2020
Occupation date13 February 2021
Location Harpenden Hertfordshire  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeDetached
Construction typeOther
Other construction typeTwo types: retrofitted cavity wall and new infill curtain wall
Party wall construction
Floor area 151
Floor area calculation method Treated Floor Area (PHPP)
Building certification  Passivhaus certified building Passivhaus certified building

Project Team

Organisation
Project lead personHeather McNeill, A D Practice Ltd
Landlord or ClientPrivate - carried out own BMS/home automation design
ArchitectHeather McNeill, A D Practice Ltd
Mechanical & electrical consultant M&E Spec & MVHR: Enhabit Ltd; Solar PV: GB-Sol Ltd; ASHP: Solid Renewables
Energy consultantHeather McNeill, A D Practice Ltd and Guy-Pitts Crick, Heatflux
Structural engineer
Quantity surveyor
ConsultantCertifier: Kym Mead, Mead: Energy & Architectural Design Ltd
ContractorJigsaw Design & Construction Ltd

Design strategies

Planned occupancyTwo people (and two cats) working from home or office-based
Space heating strategyAir source heat pump with underfloor heating downstairs and dual fuel radiators in bathrooms.
Water heating strategyAir source heat pump heating hot water tank with extra immersion element powered by solar pv. Waste water heat recovery from showers.
Fuel strategyGas free. Electricity, as much as possible generated on site
Renewable energy strategyFull front roof pitch of solar pv (8.10kW) array helping to run ASHP and heat hot water as well as powering the house and charging cars.
Passive Solar strategySouthern-facing rooms with large windows to maximise solar gain.
Space cooling strategyFan coil unit with ducted cooling into upstairs rooms. *Continuous use of MVHR with night purging in hot weather. *Electrically opening rooflights in rear extension and above stairs for stack effect purge ventilation linked to building management system.
Daylighting strategyLarge windows providing lots of natural daylighting as well as rooflights over the dining/garden room area and skylight over stair void, flooding staircase, hallway and landing with light (previously very dark).
Ventilation strategyComfort ventilation with heat recovery (winter) *Openable windows (summer) *Electrically opening rooflights in rear extension and above stairs for stack effect purge ventilation linked to building management system.
Airtightness strategy SmartPly over existing masonry structure linked to SmartPly layer in new curtain walls. *Intello Plus membrane to underside of roof.Membrane under concrete screed. *All taped together and into windows/doors
Strategy for minimising thermal bridges Thermal bridging analysis undertaken for all primary junctions interfaces. *Continuous insulation maintained throughout. *Geometric thermal bridges minimised. *External insulation wrap maintained as far as possible and compensatory insulation overrun at junctions where this is not possible. *External insulation below ground to top of foundations to prevent thermal bridging to floor/existing cavity walls.
Modelling strategyWhole house modelling was undertaken in PHPP with thermal bridges modelled by consultant in Therm
Insulation strategyNatural insulations as far as possible (not below floor slab) *External woodfibre insulation to retained cavity walls (to achieve U-value of 0.13 W/mK) *Blown Warmcel insulation in between I-studs in new curtain walls (to achieve U-value of 0.12 W/mK) *Existing floor slab renewed with 160mm PIR insulation below slab (to achieve U-value of 0.13 W/mK) *Extension floor slab with 260mm PIR PIR insulation below slab (to achieve U-value of 0.11 W/mK) *Retrofitted pitched roof with 30mm woodfibre sheathing, 240mm woodfibre insulation between rafters, 60mm woodfibre insulation below rafters (to achieve U-value of 0.135 W/mK) *Flat roof to extension with 300mm woodfibre insulation over joists (to achieve U-value of 0.12 W/mK) *EPS insulation used below ground to insulate base of walls to top of foundation level
Other relevant retrofit strategies
Contextual informationConservation area

Building services

OccupancyTwo people (and two cats) working from home or office-based
Space heatingAir source heat pump with underfloor heating downstairs and dual fuel radiators in bathrooms
Hot waterAir source heat pump heating hot water tank with extra immersion element powered by solar pv. Waste water heat recovery from showers.
VentilationBalanced ventilation system with heat recovery, enthalpy heat exchanger; heat recovery efficiency 86%
ControlsLoxone system providing whole building management system
CookingInduction hob with electric oven
Lighting100% LED
AppliancesA+ rated appliances as minimum
Renewable energy generation systemFull front roof pitch of solar pv (8.10kW) array helping to run ASHP and heat hot water as well as powering the house and charging cars with capacity for future battery installation.
Strategy for minimising thermal bridgesThermal bridging analysis undertaken for all primary junctions interfaces. *Continuous insulation maintained throughout.*Geometric thermal bridges minimised.*External insulation wrap maintained as far as possible and compensatory insulation overrun at junctions where this is not possible. *External insulation below ground to top of foundations to prevent thermal bridging to floor/existing cavity walls.

Building construction

Storeys 2
Volume 375
Thermal fabric area 503
Roof description There are two types:1) Retrofitted pitched roof:30mm woodfibre sheathing; 240mm woodfibre insulation between rafters; 60mm rigid woodfibre board; Airtight membrane; Service void; Plasterboard and skim 0.135W/m2K. 2) Flat roof to extension:100mm rigid woodfibre insulation; 200mm rigid woodfibre insulation over joists; Smartply; Service void; Plasterboard and skim 0.103W/m2K
Roof U-value 0.12 W/m² K
Walls description There are two types: 1) Retrofitted cavity wall:200mm woodfibre EWI; Existing insulated brick and block cavity wall; SmartPly; Service Void; Plasterboard and skim 0.129W/m2K. 2) New infill curtain wall: 80mm woodfibre sheathing; 300mm blown cellulose insulation between I studs; SmartPly; Service void; Plasterboard and skim.0.109W/m2K
Walls U-value 0.12 W/m² K
Party walls description N/A
Party walls U-value -
Floor description There are two types: 1) New floor slab in main house: Concrete slab; 160mm PIR insulation; Concrete screed with UFH; Floor finish. 0.127W/m2K. 2) New floor slab to rear extension: Concrete slab; 260mm PIR insulation; Concrete screed with UFH; Floor finish 0.080W/m2K
Floor U-value 0.11 W/m² K
Glazed doors description Internorm HF310 inward opening. g: 0.50; Ug: 0.53
Glazed doors U-value 0.86 W/m² K installed
Opaque doors description Internorm front door. Moralt Passiv Ferro
Opaque doors U-value 0.85 W/m² K installed
Windows description Internorm HF310 and HV450 (front and rear bedroom windows)
Windows U-value 0.86 W/m² K installed
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description Fakro DEF DU8 (flat roof extension) and Fakro FTT U8: g: 0.38; Ug: 0.40. Fakro FTT U8: g. 0.35; Ug: 0.30
Rooflights light transmittance -
Rooflights U-value 0.80 W/m² K

Harpenden EnerPHit Plus : Download Files