
Click on image to preview full size
Measured data from renewable generation is not yet available.
| Pre-development | Forecast | Measured | |
| Electricity use | 4061 kWh/yr | 3162 kWh/yr | 3915 kWh/yr |
|---|---|---|---|
| Natural gas use | 80054 kWh/yr | 10647 kWh/yr | 8407 kWh/yr |
| Oil use | - | - | - |
| LPG use | - | - | - |
| Wood use | - | - | - |
| Other Fuel | - | - | - |
| Pre-development | Forecast | Measured | |
| Primary energy requirement | 577 kWh/m².yr | 114 kWh/m².yr | 110 kWh/m².yr |
|---|---|---|---|
| Annual CO₂ emissions | 107 kg CO₂/m².yr | 23 kg CO₂/m².yr | 23 kg CO₂/m².yr |
| Annual space heat demand | - | 40 kWh/m².yr | - |
| Electricity generation | Forecast | Measured |
|---|---|---|
| Renewables Technology | - | - |
| Other Renewables Tech | - | - |
| Electricity consumed by generation | - | - |
| Primary energy requirement offset by renewable generation | 114 kWh/m².yr | 110 kWh/m².yr |
| Annual CO₂ emissions offset by renewable generation | 23 kg CO₂/m².yr | 23 kg CO₂/m².yr |
| Whole house energy calculation method | SAP |
|---|---|
| Other whole house calculation method | - |
| Energy target | Retrofit for the Future |
| Other energy targets | - |
| Forecast heating load | 7850 W/m² demand |
| Date | Result | |
| Pre-development air permeability test | - | 9.76m³/m².hr @ 50 Pascals |
|---|---|---|
| Final air permeability test | - | 3m³/m².hr @ 50 Pascals |
| Stage | Under construction |
|---|---|
| Start date | 01 March 2010 |
| Occupation date | 30 September 2010 |
| Location | Brighton East Sussex England |
| Build type | Refurbishment |
| Building sector | Public Residential |
| Property type | Detached |
| Construction type | Solid Brick |
| Other construction type | 215mm brick |
| Party wall construction | |
| Floor area | 177 m² |
| Floor area calculation method | Treated Floor Area (PHPP) |
| Building certification |
| Organisation | Earthwise Construction Ltd |
|---|---|
| Project lead person | Earthwise Construction Ltd |
| Landlord or Client | Two Piers Housing Co-Operative |
| Architect | BBM Sustainable Design Ltd |
| Mechanical & electrical consultant | Robinson Associates |
| Energy consultant | |
| Structural engineer | |
| Quantity surveyor | |
| Consultant | NBT Consult, Roger Case Design & Management, University of Brighton |
| Contractor | Earthwise Construction Ltd |
| Planned occupancy | Six bedrooms, some work at home during the week. |
|---|---|
| Space heating strategy | Heating from mains gas condensing boiler feeding radiators; Heat recovered from exhaust air using very efficient MHVR system. |
| Water heating strategy | Solar hot water from evacuated tube system; Gas condensing boiler back up. |
| Fuel strategy | Mains Gas; Mains electricity. |
| Renewable energy strategy | N/a |
| Passive Solar strategy | |
| Space cooling strategy | Natural ventilation for most of the cooling season; Daytime use of MVHR with night purging during heat waves. |
| Daylighting strategy | All kitchens achieve a minimum average daylight factor of at least 2%; All living rooms, dining rooms and studies achieve average daylight factor of at least 1.5%. |
| Ventilation strategy | Comfort ventilation with heat recovery (winter); Openable windows (summer); MVHR and window opening will be monitored. |
| Airtightness strategy | External masonry to have parge coat to provide continuous air barrier with membrane all apertures taped to ensure airtightness at critical junctions; Roof structure sealed to inside face of external masonry wall to create continuous layer; Airtight layer to be sealed to insulation layer in loft; Solid concrete ground floor slab to be taped at junctions. |
| Strategy for minimising thermal bridges | Continuous insulation maintained throughout where possible; Returns of 1m insulation where internal/external insulation of front elevation occurs; Geometric thermal bridges minimised; Thermal bridging analysis undertaken for all primary junction interfaces, in order to assist with value engineering and where possible design out / reduce mechanical fixing and where necessary low-thermal conductive fixings used; Junctions assessed include: ground floor junction, external corner, eaves, verge, window jamb, head and sill, door jamb, head and threshold. |
| Modelling strategy | Whole house modeling was undertaken in SAP and PHPP. |
| Insulation strategy | Application of external insulation to solid brick walls on north, south, and east elevations (to achieve U-value of 0.15 W/m2K); Application of internal render on street facing west elevation (to achieve U-value of 0.15 W/m2K); Insulated floating floor over existing solid cement ground slab (to achieve U-value of 0.14 W/m2K); Removal of existing mineral fibre loft insulation to create service zone, joists over boarded with insulation boards and insulation boards at rafter line (to achieve U-value of 0.10 W/m2K). |
| Other relevant retrofit strategies | We are planning to carry out our package of retrofit measures with tenants remaining in the dwelling during the proposed works; We intend to demonstrate our approach can be undertaken with minimal disruption to the tenants and with no associated temporary re-housing costs. |
| Contextual information | Energy band F - current SAP energy rating of 33; Large, but compact building form with simple external architectural detailing; Few and limited external openings, bay windows on front elevation; HMO - no hierarchy of internal spaces, bedrooms on ground and first floor; Six bedrooms, several bathrooms and a large open plan kitchen and living room, with doubling up of appliances; Existing boiler system is 'heavy', unresponsive, poorly maintained and is over 25 years old; Co-operative ownership & management by residents who are RSL; Currently has high levels of multiple occupancy with vastly differing lifestyles and requires flexibility in operation; High levels of occupancy with high electrical and water requirement issues. |
| Occupancy | NULL |
|---|---|
| Space heating | NULL |
| Hot water | NULL |
| Ventilation | NULL |
| Controls | NULL |
| Cooking | NULL |
| Lighting | NULL |
| Appliances | NULL |
| Renewable energy generation system | NULL |
| Strategy for minimising thermal bridges | NULL |
| Storeys | |
|---|---|
| Volume | - |
| Thermal fabric area | - |
| Roof description | NULL |
| Roof U-value | 0.00 W/m² K |
| Walls description | NULL |
| Walls U-value | 0.00 W/m² K |
| Party walls description | NULL |
| Party walls U-value | 0.00 W/m² K |
| Floor description | NULL |
| Floor U-value | 0.00 W/m² K |
| Glazed doors description | NULL |
| Glazed doors U-value | 0.00 W/m² K - |
| Opaque doors description | NULL |
| Opaque doors U-value | 0.00 W/m² K - |
| Windows description | NULL |
| Windows U-value | 0.00 W/m² K - |
| Windows energy transmittance (G-value) | - |
| Windows light transmittance | - |
| Rooflights description | NULL |
| Rooflights light transmittance | - |
| Rooflights U-value | 0.00 W/m² K |